Budapest, Határ Road sewer reconstruction
The project entailed the following works:
Reconstructing 1204.7 m of (30/45 t/b section) main sewer network with soft lining,
Constructing 45.7 m of Ø 40 KG PVC main sewer line with open-ditch method,
Constructing 28 m of Ø 30 KG PVC main sewer line with open-ditch method,
Building two circular cleaning manholes,
Constructing 228 m of Ø 15 KG PVC domestic sewer connections with open-ditch method,
Installing 46 NA 300 KG PVC cleaning hatches
Starting date: 01/01/2006Kezdés: 2006.01.01.
Completion date: 31/12/2006Befejezés: 2006.12.31.