Torching on the M85

2014. 07. 18..

On the Enese-Csorna section of the M85 currently under construction, pipe torching took place on 29 May 2014, rendered necessary by the link-up of the relocated section on the crossing DN400 PN64 high-pressure natural gas steel pipeline. The milestone – having an effect on the final deadline of the entire project – was accomplished by emptying the pipeline and torching the gas at the Csorna gas transfer station at 7:30 am.