M25 expressway, southern section 1 (M3-Kerecsend) - Colas Közlekedésépítő
M25 expressway, southern section 1 (M3-Kerecsend)
We are currently working on connecting the city of Eger to Hungary’s high-speed road network with a 2×2-lane road, which is being implemented in two distinct phases. Colas Út Zrt. (as a member of a consortium led by He-Do Kft.) signed the contract for the northern part of phase 2 on 20 December 2017. Simultaneously, Colas Út entered into a separate agreement for building the southern part of phase 2.
The overall value of phase 2 – the parts of which are separated by main road 3 – is 35.76 billion forints, and the share of the involved Colas subsidiaries amounts to 27.41 billion.

Client: Nemzeti Infrastruktúra Fejlesztő Zrt.

Starting date: 01/10/2017Kezdés: 2017.10.01.

Completion date: 20/12/2019Befejezés: 2019.12.20.

Location: Heves megye

Length: 7.1 kmHossz: 7.1 km
Asphalt: 27 400 tAszfalt: 27 400 t
Concrete: 25 000 m3Beton: 25 000 m3
Earthworks: 1 248 000 m3Földmunka: 1 248 000 m3
Number of structures: 4Műtárgyak száma: 4
Colas Hungária