On 20 April 2022, the foundation stone of the Drégelypalánk Ipoly Bridge was laid, the new border bridge was built by Colas, and our company also carried out the connecting road works. With the construction of the bridge, a new crossing point between Slovakia and Hungary will be created, facilitating the transport of residents and strengthening the links between the two countries. The 50-metre steel bridge is open to passenger traffic and goods traffic up to 3.5 tonnes.
Completion of the technical handover: 20.09.2023.
Project closure with press conference: 12.01.2024.
Client: NIF Zrt.
Starting date: 29/10/2021Kezdés: 2021.10.29.
Completion date: 20/09/2023Befejezés: 2023.09.20.
Location: Drégelypalánk
Section: 72+946 Szelvény: 72+946
Steel structures: 50 mAcélszerkezet: 50 m
Steel structures: 50 mAcélszerkezet: 50 m