M0-M7 motorway interchange reconstruction - Colas Közlekedésépítő
M0-M7 motorway interchange reconstruction
During the reconstruction of the interchange of motorways M0 and M7, new public road connection will be built in the vicinity of Törökbálint and Érd between road 8103(Dózsa György Street) and the interchange of motorways M0-M7. Within the project 30 000 m3 earthworks will be constructed, 6000 t asphalt will be laid and 2 bridges will be renewed. Road 8103 will be reconstructed on a 690 meter length. In the area of the interchange 45 000 m2 of forest will be planted.

Client: Nemzeti Infrastruktúra Fejlesztő Zrt.

Starting date: 04/04/2015Kezdés: 2015.04.04.

Completion date: 04/04/2016Befejezés: 2016.04.04.

Length: 900 mHossz: 900 m
Asphalt: 6 000 tAszfalt: 6 000 t
Earthworks: 30 000 m3Földmunka: 30 000 m3
Number of structures: 2Műtárgyak száma: 2
Colas Hungária