Beams installed on M35 nighttime

2017. 05. 12..

32 units of 30.8-metre-long FCI-120 beams were lifted to place at the bridge of the M35 motorway above main road 4. The beam installation of spans ‘B’ and ‘C’ at overpass 439 took just over 10 hours on the night of 12 May under a sequence of lane closures managed by the local police.