The weakest link of the concept proved to be the load bearing of the old bridge. Subsequent to taking over the site in April, we subjected the structure to a wide range of destructive tests, and found that it had suffered damages that rendered the original plans infeasible. At this point, the construction process took a sharp turn, and we drew up a plan for a detour and a temporary bridge in just a few weeks. After convincing the decisionmakers, design works commenced in May, and by the end of August, we managed to build a detour with the adjoining 60-metre-long TMM-3 vehicle-launched military bridge, including the obtainment of the necessary permits from the Traffic Authority.
Starting date: 28/04/2018Kezdés: 2018.04.28.
Completion date: 28/12/2018Befejezés: 2018.12.28.
Location: Sajópüspöki