Göd - construction of industrial and drinking water transmission lines
Technical data: water supply, planned daily industrial water demand: 24 000 m3/day, planned daily drinking water demand: 3 000 m3/day

Drinking water pipeline construction:
– D315 KPE pipe 8 796 fm
– 1 intermittent gate valve
– interceptor manhole 6 pcs.
– 7 ventilation manholes
– discharge manhole 8 pcs

Industrial water pipeline construction:
– DN 600 GÖV pipe 8 583 fm
– D 710 KPE 324 fm
– Sliding gate valve 1 piece
– manhole 6 pcs.
– ventilation manhole 7 pcs
– discharge manhole 8 pcs

Client: DMRV Duna Menti Regionális Vízmű Zrt.)

Starting date: 03/10/2023Kezdés: 2023.10.03.

Completion date: 30/04/2024Befejezés: 2024.04.30.

Location: Göd

Colas Hungária