Sewer construciton in Érd and the surrounding areas
The complete investment includes over 320 km of backbone pipeline with the related pressurised network, as well as approximately 22 000 domestic connections and the construction of 16 kilometres of service roads.
- 30 km gravity drains: DN 200-400mm KG-PVC
- 5 km of pressurised sections: D63-315 KPE
- 2113 domestic connections
- 900 m of service roads
Client: Érd és Térsége Szennyvízelvezetési és Szennyvíztisztítási Önkormányzíti Társulás
Starting date: 20/10/2011Kezdés: 2011.10.20.
Completion date: 02/06/2014Befejezés: 2014.06.02.
Location: Érd
Number of home connections: 2 113Házi bekötések száma: 2 113