2020. 10. 21..
Everything on the section of the M30 motorway under construction between Szikszó and Encs is on schedule. The readiness of earthworks for the main track is currently at 90%. The track structure is constantly being built. The Ckt layer was built at almost 16 km, on which the base and binding layers were added in several places. Construction of the wear layer is also expected to begin in September. It is planned that by half of the 24.5-kilometer section, the top layer of asphalt will be paved by the end of the year.
In addition to the route, 2 mines and 2 target producers were opened for earthworks, of which a total of more than 1.5 million m3 of aggregate is installed.
Sand is supplied from 3 mines. The total amount to be installed is 1.5 million tons.
In addition, there is a concrete plant in Szikszó, Csobád and Encs. The total amount of asphalt required for the implementation of the project will be provided by the new mixer in Felsőzsolca.
Next to Csobád, a complex rest area will be built on both sides, where in addition to the usual toilet building, there will also be a playground and a fitness park. The motorway will be operated by the Motorway Engineering Plant to be established at Encs.
The role of the M30 road network is twofold: on one hand, it connects Miskolc, the third most populous city in the country, to the Hungarian network, and it also plays a significant role in the European road network.
The deadline for the completion of the technical handover procedure is 31 August 2021.