11.5-tonne pavement reinforcement on main road 76
The project – divided into 11 separate work sites – required Colas Út Zrt. to reconstruct a 26.7-km-long section of main road 76 until the November 2011 completion deadline.
The job entailed pavement reinforcement on 26.2 km, and 50-cm pavement widening on 21.4 km. We built 13 junctions, two of which were roundabouts. Simultaneously, we widened and remodelled three bridges, built four traffic-calming islands and installed stormwater drains on a length of 2.2 km.
The new pavement structure of the road is made up of 4 cm SMA 11 (F) modified asphalt, 9 cm AC 22 (F) modified asphalt, asphalt reinforcing grid, 7 cm AC 22 NM modified base asphalt, 20 cm Ckt road base, and 20 cm sandy gravel.
Starting date: 23/09/2009Kezdés: 2009.09.23.
Completion date: 18/11/2011Befejezés: 2011.11.18.
Length: 26.7 kmHossz: 26.7 km
Number of lanes: 2x1Sávok száma: 2x1
Asphalt: 121 000 tAszfalt: 121 000 t
Concrete: 32 362 m3Beton: 32 362 m3
Earthworks: 423 672 m3Földmunka: 423 672 m3
Number of lanes: 2x1Sávok száma: 2x1
Asphalt: 121 000 tAszfalt: 121 000 t
Concrete: 32 362 m3Beton: 32 362 m3
Earthworks: 423 672 m3Földmunka: 423 672 m3