Construction of passing lanes on main road 21
Starting out in the centre of Hatvan and crossing the M3 motorway, main road 21 runs north towards Salgótarján in the valley of the Zagyva River. As traffic kept growing heavier, the risk of accidents also increased. To provide a solution, two passing sections were constructed 5 km apart in a length of approximately 2 km, respectively. In line with the corresponding contract, the existing 2×1 lane legs were widened to 2×2 lanes.
Starting date: 20/05/2009Kezdés: 2009.05.20.
Completion date: 13/10/2010Befejezés: 2010.10.13.
Location: Lőrinci
Asphalt: 14 000 m3Aszfalt: 14 000 m3
Concrete: 9 700 m3Beton: 9 700 m3
Earthworks: 155 000 m3Földmunka: 155 000 m3
Concrete: 9 700 m3Beton: 9 700 m3
Earthworks: 155 000 m3Földmunka: 155 000 m3