M4 motorway, Phase 2 (Albertirsa-Cegléd)
The consortium uniting Colas Út Zrt. (as consortium leader), Colas Közlekedésépítő Zrt. and Colas Hungária Zrt. was engaged by the client in December 2016, opening the way for activities to commence in spring 2017. With an overall contractual value of HUF 20.5 billion, the project is respectable among the jobs secured by Hungarian Colas subsidiaries in recent years.
However, the tasks at hand are not without complications: our crews had to work within traffic on one of the country’s busiest roads, while also keeping 2×1 lanes open for motorists at all times. As part of the investment, Main Road 4 has been widened to 2×2 lanes on nearly 14.5 kilometres between chainages 58+821 and 73+235. Meanwhile, we were building four brand new multi-level interchanges and a pair of complex rest areas by expanding two existing MOL filling stations.

Client: Nemzeti Infrastruktúra Fejlesztő Zrt.

Starting date: 30/04/2017Kezdés: 2017.04.30.

Completion date: 31/08/2019Befejezés: 2019.08.31.

Length: 14.4 kmHossz: 14.4 km
Section: 58+821-73+235Szelvény: 58+821-73+235
Asphalt: 129 800 tAszfalt: 129 800 t
Earthworks: 1 070 700 m3Földmunka: 1 070 700 m3
Number of structures: 6Műtárgyak száma: 6