On 1 July 2016, we signed a contract with Grabarics Kft. for carrying out road-construction works at the production plant of Thyssenkrupp in Jászfényszaru. The time frame available for the job was very limited, with a deadline of early 2017. The project requires us to install some 3,600 cubic metres of Ckt road base, build over 20,000 square metres of decorative paving, and construct 4,700 metres of curbs.

Client: Grabarics Építő Kft.

Starting date: 10/07/2016Kezdés: 2016.07.10.

Completion date: 31/03/2017Befejezés: 2017.03.31.

Location: Jászfényszaru

Concrete: 3 600 m3Beton: 3 600 m3
Kerbstone: 4 700 mSzegély: 4 700 m
Pavers: 20 000 m2Térkő: 20 000 m2