Peron underpass construction Taksony, Délegyháza, Kiskunlacháza
The largest volume of work is taking place at the Délegyháza station, where three lift shafts, three staircases and a fifty-metre-long pedestrian underpass consisting of three dilatation units are being built. In addition, a cleaning room will soon be completed at all three stations. The construction of the underpass in Délegyháza was delayed by six weeks because the client has modified the plans in the meantime, resulting in a longer structure than originally planned.

The works at all three sites had to be carried out in groundwater to a depth of four metres for the underpasses and six metres for the lift shafts. The work areas were delimited by reed panels to prevent water ingress. Another challenge in Kiskunlacháza was that the works had to be carried out in two phases. A technical challenge was to connect the work area and the groundwater level lowering when changing the phase. During the works, we ensured that construction traffic on a railway track was not disrupted at any time. In Kiskunlacháza, for example, this was done by anchoring the reed plates. In addition to the passage of railway trains near the work site, we also had to maintain the access road for the transport of the contractors.

Starting date: 14/06/2023Kezdés: 2023.06.14.

Completion date: 30/11/2024Befejezés: 2024.11.30.

Structural concrete: 1200 m3Szerkezeti beton: 1200 m3
Concrete steel: 210 tonsBetonacél: 210 tons
Colas Hungária